Turkey has completed the initial stage of the tender process for a new railway that will directly connect Istanbul Airport (IST) and Sabiha Gökçen Airport (SAW). On November 11, the project received 25 bids from Turkish and international contractors. Trains will cross the Bosphorus via the Yavuz Sultan Selim Bridge.

Route and Project Scale

The Istanbul Northern Rail Crossing (INRAIL) project is being developed by Turkey’s Ministry of Transport and Infrastructure. It involves the construction of an approximately 125 km double-track electrified railway.

The line will begin in Çayırova, near Gebze, and continue through Sabiha Gökçen Airport, the Yavuz Sultan Selim Bridge, and Istanbul Airport before terminating in Çatalca. There, it will connect with the Halkalı–Çerkezköy high-speed railway, which is currently under construction.

The route will include 44 tunnels with a combined length of 59.1 km, as well as 42 bridges and viaducts totaling 22.4 km. Once operational, the railway is expected to accommodate up to 33 million passengers and 30 million tonnes of freight annually.

What Will Change for Passengers

For the first time, the two airports will have a direct railway connection. Public transport travel time between them is expected to decrease from approximately 120 minutes to 65 minutes, making transfers between flights at different airports significantly more convenient.

The new line will also reduce pressure on Marmaray, the railway tunnel beneath the Bosphorus currently used by both passenger and freight trains.

Financing and Contractors

The project has secured $6.75 billion in financing from six international financial institutions. According to Transport and Infrastructure Minister Abdulkadir Uraloğlu, it is Turkey’s largest railway project financed through external funding.

Construction has been divided into four sections. Leading Turkish construction companies submitted bids, along with four foreign companies from China and Italy.

Contractors have not yet been selected. The evaluation committee will first assess technical proposals, followed by financial bids. The construction start date and the railway’s opening schedule have not yet been announced.

What This Means for the Real Estate Market

Although the project is still at the tender stage, it could significantly transform Istanbul’s transport connectivity in the future. Accessibility remains one of the key factors for property buyers, with international buyers increasingly considering districts with convenient transport links, such as Başakşehir and Ataşehir.

Umbrella Group specialists can help clients select real estate in Istanbul, taking into account transport accessibility and future district development plans.